MCL Contracting improves roadwork method using SDLG

August 22, 2016

MCL Contracting improves roadwork method using SDLG

The Texas-based company has a newly improved method of placing continually reinforced concrete paving steel using SDLG wheel loaders, helping it to cut costs, provide a safer work environment and attract new talent.

MCL Contracting purchased its first two SDLG wheel loaders much like any other typical customer. Working in the concrete paving industry, the Richland Hills, Texas-based company only needed a loader for three to four hours each day and require the features of a premium machine.

What began as routine wheel loader purchases, though, soon turned into lucrative capital investments, as the company began using the loaders to work out an improved method of placing rebar for continually reinforced concrete paving. Using its two SDLG wheel loaders in conjunction with other equipment, MCL has dramatically reduced the difficulty of its operations and reduced cost.

We first purchased the SDLG wheel loaders to unload trucks of rebar at the job site when placing reinforcing steel for concrete paving; explained Megan LaPointe, president of MCL. We were dependent on the general contractor to unload and move heavy rebar on the job site and vulnerable to their schedule, so we wanted to get a little more control over our operations. We only needed the wheel loaders working a few hours each day, so purchasing more expensive loaders make sense.

MCL had the loaders fitted with 12 ft forks to move 40 ft bundles of rebar around the job site, many of the loads weighing up to 6 USt. The company chose the 4.0 yd3 capacity SDLG LG959 model to meet its capacity needs. By using the wheel loaders instead of having a crew manually lift rebar sections, MCL was able to save at least one hour of unloading for each truckload. The move immediately began to save both time and money for MCL three trucks per day, the company began shaving off three hours of unloading time a day. 

The SDLG really held its own against what we expect from a premium model with a higher price point, LaPointe explained. We probably only have a 40% utilization rate, and sometimes the machine might even sit for a week or two. It fits our needs perfectly. We‘ve had no downtime or repair costs to deal with, either.

 Megan LaPointe, president of MCL Contracting


Paving a new way

Shaving a few hours each day from MCL’s material handling duties was only the beginning. Soon the company began to integrate the machine more into its rebar paving projects. In conjunction with a Combilift, a multi-directional forklift, MCL began using the SDLG wheel loader to automate its roadwork processes.

Reinforced concrete rebar paving has always been a manual labor job the crew carried the rebar from bundles on the jobsite, and then positioned them in a place to be tied, LaPointe explained. We have made it more automated with the SDLG wheel loaders.

MCL uses an SDLG wheel loader and the Combilift, which can swivel in various directions, to dual-lift the rebar and dual-carry it into place. The SDLG is fitted with a forklift attachment, and with the Combilift, MCL uses the four forks from both machines with a spreader bar to ensure the rebar is held and placed evenly. The rebar is then guided by hand toward the ground.

The individual segments of rebar weigh about 60 lbs each, they’re heavy, and by using the wheel loader and multi-directional forklift, the process minimizes potential injuries. This makes the job less physically demanding, LaPointe said. And we’ve been able to reduce our crew needs by half. We used to need 10 to 12 guys per job, now we only need six to eight, which has again reduced our costs.

The ease in physical labor has not only made the job site more efficient, it has enabled the company to attract a younger workforce. A well-cited problem in construction and manufacturing, companies often find difficulty in replacing their aging workforces. LaPointe said that hiring has become less difficult because the job is not as physically abusive.

MCL purchased the two SDLG wheel loaders from Dallas-based Romco Equipment, with which the company has done business several times. LaPointe said buying the equipment from a dealer the company knows and respects gave it the confidence to take a chance on SDLG. In fact, MCL had initially only purchased one SDLG loader, and it performed so well that the company bought a second a few months later.

MCL Contracting, LLC, is an official woman-owned business that has operated in Texas for five years. It is a subcontractor that specializes in rebar installation. 


 

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349,18701576687
lmjx.net Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China